Works continue at DiONE

We remain in the set schedule and aim to deliver DiONE ready by the end of 2020.

BCL PRO Team

25/09/2019

A summary of works that have been done to date at DiONE construction site:

Foundation slab – completed
Basement slab – completed

During the first week of October 2019 pouring of concrete should be carried by the general contractor at the ground floor and mid of October 2019 the framework of the ground floor should be completed. By the end of October 2019 the first floor slab should be set and works progress to creating the columns and beams. We remain in the set schedule and aim to deliver DiONE ready by the end of 2020.